AIMS Attachment A: AIMS Statement of Work
Page 121 of 130
5. Power supplies to be connected to the system and equipment have
been verified as the correct voltage, phasing, and frequency as
indicated.
B. Satisfaction of the above requirements shall not relieve the
CONTRACTOR of responsibility for incorrect installations, defective
equipment items, or collateral damage as a result of CONTRACTOR
work/equipment.
4.2 TESTING REQUIREMENTS
4.2.1 General
A. Testing Steps:
1. On-Site Factory Acceptance Testing
2. On-Site Performance Verification Testing
3. On-Site Endurance Testing
B. Test Plan/Procedure: The CONTRACTOR shall provide six (6)
hardcopies and an electronic copy of the test plan/procedures for each
testing phase for the review and approval of the County. The test plan for
each phase shall detail the objectives of all tests. The tests shall clearly
demonstrate that the system and its components fully comply with the
requirements specified herein. The test plan shall be provided at least
forty-five (45) calendar days prior to the scheduled start of each test. Test
plans shall contain at a minimum:
1. Functional procedures including use of any test equipment
2. Test equipment is to be identified by manufacturer and model
3. Interconnection of test equipment and steps of operation shall be
defined
4. Test records shall include test equipment serial number, calibration
date and calibration certification of test equipment
5. Expected results required to comply with specifications
6. Traceability matrix referencing specification requirements with specific
test procedures
7. Record of test results with witness initials or signature and date
performed
8. Pass or fail evaluation with comments.